1、 |
Civil Work of the Weir: |
|
〈1〉 |
Abstraction and Discharge Channel Work
Quantity of Abstraction:35CMS
Design Level of Abstraction:EL 16.00m
1.Inlet:
Inlet Width:111m(Including piers and columns)
Screen: 7.0m*2.0m*14 units
2.Side-Path Discharge Channel:
Design Discharge Quantity:37CMS
Sluice Gate:4.0 m*2.0 m*3 gates
3.Side Channel Water Abstraction Work:
Spillweir Crest:EL 15.5m
Spill Width:100m
Sluice Gate:4.0 m*2.0 m*3 gates
4.Grit Chamber:42 m*75 m
Type:Single tank, mechanical discharge |
〈2〉 |
Water Intercept Weir Work
1.Grit Discharge Channel:
70 m, rubber dam 30m W*2.5 m H*2 gates, rubber dam crest EL 16.0m. design lodging level EL 16.4m.
2.Movable Weir:
216m, deflatable rubber dam 6 gates, rubber dam crest EL 16.0 m, design lodging level EL 16.4 m.
3.Fixed Weir:
674m, concrete dam, dam crest EL 17.0m、17.8m and 18.5m |
|
〈3〉 |
Downstream Bed Protection:
Type:
3m*3m*3m and 3m*5m concrete blocks and 10T concrete dolosses.
Quantity:3 courses, 45m each, spaced at 100m. |
|
〈4〉 |
Upstream and Downstream-Connection Work:
Flood wall 402 m
Retaining embankment 235 m |
|
〈5〉 |
High Sand Low Water Retaining Embankment:1000m |
|
〈6〉 |
Wu Luo Creek Retaining Embankment Work:1820m, with Nonglu Bridge. |
|
〈7〉 |
Fish Ladder:30 m long, 1.2 m wide, slope 1/15 |
|
〈8〉 |
Control Room and Management Office Work |
2、 |
Rubber Dam Work for the Water Intercept Weir: |
|
Rubber Dam 8 Sets |
Dams No. 1 & No. 2 - 2.0m (H)*40m
Dams No. 3 & No. 4 - 2.5m (H)*30m
Dams No. 5 & No. 6 - 2.5m (H)*20m
Dams No. 7 & No. 8 - 2.5m (H)*30m |
3、 |
Electrical and Mechanical Work of the Water Intercept Weir: |
|
|
1.Gate and Electrical Equipment |
|
|
2.Remote Monitoring System |
4、 |
Pumping Station Work: |
|
|
One set, undertaken by the water corporation. |
5、 |
River Regulation Work: |
|
|
1. From Liling Bridge to the inundated area upstream of the river intercept weir, about 9km.
2.The left bank upstream of the water intercept weir and the right and left banks downstream, about 2km each. |
6、 |
Arrangement of the Surrounding Environment: |
|
|
Completed in December 1999. |
7、 |
Wuluo Creek Retaining Embankment Extension Work: |
|
|
Completed in June 1999. |